HAYEK INTERCHANGE BRIDGE

Client: CMC / JALKH J.V.

The share of Int’l IGM in this project was to design the piles & perform the required tests:

  • Ultimate Static load test (280 Ton = 200% of design load) according to ASTM D 1143.
  • Construction of the test piles (1m diameter 10.5m length).
  • Construction of the steel reaction beams.
  • Construction of 10 ground Anchors around the test pile to attain the ultimate load.
  • Jack & gauges Calibration.
  • Service piles Static load test (210 Ton = 150% of design load) according to ASTM D 1143.
  • Piles integrity tests: PIT, according to the frequency required.
  • Perform the test in accordance to International Standards and under the supervision of the Consultant.