TAWK BUILDING

Client: Mr. HANNA TAWK

The Project in Fanar consists of supporting a permanent excavation after a slope failure occurrence. The failure occurred in the cemented sandy soil after heavy rains due to unsupported excavation > 15m height. The remedial solution was to first backfill the area, prepare a platform, and drill 60cm diameter piles curtain. The piles are then supported by permanent active anchors and a shotcrete face. The anchors were grouted under pressure (IRS System) and well protected.

Design

22-01-05c

22-01-05

11-29-04I

Tawk 1

Tawk 3